Induction
All workers to be inducted via 1breadcrumb.
Visitors are to register their attendance via 1breadcrumb and always be accompanied by a member of the Scope Projects site management team.
Site Access/Security
Daily sign in/out required via 1breadcrumb.
Site Manager to be notified of any out of hours work.
HRW SWMS
For all high risk work, SWMS are to be submitted to 1breadcrumb for review by the Scope Projects site management team and accepted prior to commencing work.
PPE
Minimum - High-vis vest & safety boots.
All other PPE based on task or as identified in the SWMS.
Incidents
All incidents to be reported immediately to the site manager.
Electrical
Only licensed electricians are permitted to modify or move any cables.
All cables to be treated as live.
Behaviour
Everyone is to conduct themselves in a respectful manner to fellow workers, project team, clients, tenants and members of the public.
Housekeeping
Always keep site clean and tidy.
Construction waste to be removed on a regular basis or as instructed by Scope Projects site management team.
Food/drink waste to be placed in designated bins.
Noise
Hammer drilling, jack hammering, etc only permitted between the hours nominated for noisy work.
Radios to be kept at a low level.